The absolute size of a variance is more important than the relative size when trying to decide what variances to investigate.

Correct Answer

verifed

verified

Variances are computed by taking the difference between which of the following?


A) Product cost and period cost.
B) Actual cost and differential cost.
C) Price factors and rate factors.
D) Actual cost and standard cost.
E) Product cost and standard cost.

Correct Answer

verifed

verified

The individual generally responsible for the direct-material price variance is the:


A) sales manager.
B) production supervisor.
C) purchasing manager.
D) finance manager.
E) head of the human resources department.

Correct Answer

verifed

verified

The aggregate nature of the variances in standard costing is a drawback in the advanced manufacturing setting that makes it difficult for managers to determine their cause.

Correct Answer

verifed

verified

Lamar Corporation's purchasing manager obtained a special price on an aluminum alloy from a new supplier, resulting in a direct-material price variance of $9,500F. The alloy produced more waste than normal, as evidenced by a direct-material quantity variance of $2,000U, and was also difficult to use. This slowed worker efficiency, generating a $2,500U labor efficiency variance. To help remedy the situation, the production manager used senior line employees, which gave rise to a $900U labor rate variance. If overall product quality did not suffer, what variance amount is best used in judging the appropriateness of the purchasing manager's decision to acquire substandard material?


A) $4,100F.
B) $5,000F.
C) $7,000F.
D) $7,500F.
E) $9,500F.

Correct Answer

verifed

verified

Which of the following are methods for setting standards?


A) Analysis of historical data and goal congruence.
B) Task analysis and matrix application forms.
C) Task analysis and the analysis of historical data.
D) Matrix application forms and analysis of historical data.
E) Goal congruence and task analysis.

Correct Answer

verifed

verified

A statistical control chart is best used for determining:


A) direct-material price variances.
B) direct-labor variances.
C) whether a variance is favorable or unfavorable.
D) who should be held accountable for specific variances.
E) whether a particular variance should be investigated.

Correct Answer

verifed

verified

When the quantity of materials purchased is not equal to the quantity of material used, most companies base the calculation of the material quantity variance on the:


A) quantity of direct materials purchased.
B) quantity of direct materials spoiled.
C) quantity of direct materials that should have been used in achieving actual production.
D) quantity of direct materials actually used.
E) None of the answers is correct.

Correct Answer

verifed

verified

Timber Enterprises purchased 67,000 pounds (cost = $616,400) of direct material to be used in the manufacture of the company's only product. According to the production specifications, each completed unit requires four pounds of direct material at a standard cost of $9 per pound. Direct materials consumed by the end of the period totaled 65,500 pounds in the manufacture of 16,050 finished units. An examination of Timber's payroll records revealed that the company worked 42,000 labor hours (cost = $621,600) during the period, and specifications called for each completed unit requiring 2.6 hours of labor at a standard cost of $15 per hour. Assume that the company computes variances at the earliest point in time. Required: Calculate the direct-material price and quantity variances, and the direct-labor rate and efficiency variances. Indicate whether each variance is favorable or unfavorable.

Correct Answer

verifed

verified

Direct Material Price Variance: 65,500 x...

View Answer

A direct-labor efficiency variance cannot be caused by:


A) inexperienced employees.
B) poor quality raw materials.
C) employee inefficiency.
D) an out-of-date labor time standard.
E) producing fewer finished units than originally planned.

Correct Answer

verifed

verified

Venazio Products uses a standard costing system to assist in the evaluation of operations. The company has had considerable employee difficulties in recent months, so much so that management has hired a new production supervisor (Ralph Moreno). Moreno has been on the job for six months and has seemingly brought order to an otherwise chaotic situation. The vice-president of manufacturing recently commented that "Moreno has really done the trick. Ralph's team-building/morale-boosting exercises have truly brought things under control." The vice-president's comments were based on both a plant tour, where he observed a contented work force, and review of a performance report that showed a total labor variance of $14,000F. This variance is truly outstanding, given that it is less than 2% of the company's budgeted labor cost. Additional data follow. ยท Total completed production amounted to 20,000 units. ยท A review of the firm's standard cost records found that each completed unit requires 2.75 hours of labor at $14 per hour. Venazio's production actually required 42,000 labor hours at a total cost of $756,000. Required: A. As judged by the information contained in the performance report, should the vice-president be concerned about the company's labor variances? Why? B. Calculate Venazio's direct-labor variances. C. On the basis of your answers to requirement "B," should Venazio be concerned about its labor situation? Why? D. Briefly analyze and explain the direct-labor variances.

Correct Answer

verifed

verified

A. No. The variance is favorable and sma...

View Answer

Product costing is the process of accumulating the costs of a production process and assigning them to the completed products.

Correct Answer

verifed

verified

A favorable labor efficiency variance is created when:


A) actual labor hours worked exceed standard hours allowed.
B) actual hours worked are less than standard hours allowed.
C) actual wages paid are less than amounts that should have been paid.
D) actual units produced exceed budgeted production levels.
E) actual units produced exceed standard hours allowed.

Correct Answer

verifed

verified

During June, Fraser Company's material purchases amounted to 6,000 pounds at a price of $7.35 per pound. Actual costs incurred in the production of 2,000 units were as follows: During June, Fraser Company's material purchases amounted to 6,000 pounds at a price of $7.35 per pound. Actual costs incurred in the production of 2,000 units were as follows:     The standards for one unit of Fraser Company's product are as follows:    Required:  Compute the direct-material price and quantity variances, the direct-material purchase price variance, and the direct-labor rate and efficiency variances. Indicate whether each variance is favorable or unfavorable.  The standards for one unit of Fraser Company's product are as follows: During June, Fraser Company's material purchases amounted to 6,000 pounds at a price of $7.35 per pound. Actual costs incurred in the production of 2,000 units were as follows:     The standards for one unit of Fraser Company's product are as follows:    Required:  Compute the direct-material price and quantity variances, the direct-material purchase price variance, and the direct-labor rate and efficiency variances. Indicate whether each variance is favorable or unfavorable.  Required: Compute the direct-material price and quantity variances, the direct-material purchase price variance, and the direct-labor rate and efficiency variances. Indicate whether each variance is favorable or unfavorable.

Correct Answer

verifed

verified

A perfection standard:


A) tends to motivate employees over a long period of time.
B) is attainable in an ideal operating environment.
C) would make allowances for normal amounts of scrap and waste.
D) is generally preferred by behavioral scientists.
E) will result in a number of favorable variances on a performance report.

Correct Answer

verifed

verified

Managerial accountants use either task analysis or an analysis of historical data to set cost standards.

Correct Answer

verifed

verified

Quinton Company has set the following standards for one unit of product: Direct material Quantity: 6.2 pounds per unit Price per pound: $11 per pound Direct labor Quantity: 6 hours per unit Rate per hour: $23 per hour Actual costs incurred in the production of 2,800 units were as follows: Direct material: $194,350 ($11.50 per pound) Direct labor: $393,750 ($22.50 per hour) All materials purchased were consumed during the period. Required: Calculate the direct-material price and quantity variances, and the direct-labor rate and efficiency variances. Indicate whether each variance is favorable or unfavorable.

Correct Answer

verifed

verified

James at the Mill Barn Woods produces handcrafted frames. A standard-size 11 x 14 inch frame requires 6 board feet of rustic barn wood in the finished product. In addition, 1 board foot of scrap lumber is normally left from the production of one frame. James pays a demolition company $1.50 per board foot, plus $1.00 in transportation charges per board foot. Required: Compute the standard direct-material cost of a frame.

Correct Answer

verifed

verified

Which of the following choices correctly indicates the use of the standard price per unit of direct material when calculating the materials price variance and the material quantity variance? Price Variance Quantity Variance


A) Used Always used
B) Used Occasionally used
C) Used Not used
D) Not used Always used
E) Not used Not used

Correct Answer

verifed

verified

Action Enterprises recently used 14,000 labor hours to produce 7,500 completed units. According to manufacturing specifications, each unit is anticipated to take two hours to complete. The company's actual payroll cost amounted to $158,200. If the standard labor cost per hour is $11, Action's labor rate variance is:


A) $4,200U.
B) $4,000F.
C) $4,300U.
D) $4,300F.
E) None of the answers is correct.