Filters
Question type

Study Flashcards

In Zero Company's income statement, they report actual gross profit of $52,500 and the following variances:  Materials price $420 F Materials quantity 600 F Labor price 420U Labor quantity 1,000 F Overhead 900 F\begin{array} { l r r } \text { Materials price } & \$ 420 \mathrm {~F} \\\text { Materials quantity } & 600 \mathrm {~F} \\\text { Labor price } & 420 \mathrm { U } \\\text { Labor quantity } & 1,000 \mathrm {~F} \\\text { Overhead } & 900 \mathrm {~F}\end{array} Zero would report gross profit at standard of


A) $46,660.
B) $47,500.
C) $55,000.
D) $53,340.

Correct Answer

verifed

verified

Using standard costs


A) makes employees less "cost-conscious."
B) provides a basis for evaluating cost control.
C) makes management by exception more difficult.
D) increases clerical costs.

Correct Answer

verifed

verified

In developing a standard cost for direct materials, a price factor and a quantity factor must be considered.

Correct Answer

verifed

verified

A company uses 20,000 pounds of materials for which it paid $6.00 a pound.The materials price variance was $15,000 unfavorable.What is the standard price per pound?


A) $0.75
B) $5.25
C) $6.00
D) $6.75

Correct Answer

verifed

verified

The predetermined overhead rate for Zane Company is $5, comprised of a variable overhead rate of $3 and a fixed rate of $2.The amount of budgeted overhead costs at normal capacity of $150,000 was divided by normal capacity of 30,000 direct labor hours, to arrive at the predetermined overhead rate of $5.Actual overhead for June was $9,500 variable and $6,050 fixed, and standard hours allowed for the product produced in June was 3,000 hours. The total overhead variance is


A) $3,050 F.
B) $550 F.
C) $550 U.
D) $3,050 U.

Correct Answer

verifed

verified

Which one of the following describes the total overhead variance?


A) The difference between what was actually incurred and the flexible budget amount
B) The difference between what was actually incurred and overhead applied
C) The difference between the overhead applied and the flexible budget amount
D) The difference between what was actually incurred and the total production budget

Correct Answer

verifed

verified

The customer perspective of the balanced scorecard approach


A) is the most traditional view of the company.
B) evaluates the internal operating processes critical to the success of the organization.
C) evaluates how well the company develops and retains its employees.
D) evaluates the company from the viewpoint of those people who buy its products or services.

Correct Answer

verifed

verified

Allowance for spoilage is part of the direct


A) materials price standard.
B) materials quantity standard.
C) labor price standard.
D) labor quantity standard.

Correct Answer

verifed

verified

The balanced scorecard


A) incorporates financial and nonfinancial measures in an integrated system.
B) is based on financial measures.
C) is based on nonfinancial measures.
D) does not use financial or nonfinancial measures.

Correct Answer

verifed

verified

The overhead volume variance relates only to fixed overhead costs.

Correct Answer

verifed

verified

If actual costs are greater than standard costs, there is a(n)


A) normal variance.
B) unfavorable variance.
C) favorable variance.
D) error in the accounting system.

Correct Answer

verifed

verified

Standard cost is the industry average cost for a particular item.

Correct Answer

verifed

verified

The starting point for determining the causes of an unfavorable materials price variance is the purchasing department.

Correct Answer

verifed

verified

Which of the following is not considered an advantage of using standard costs?


A) Standard costs can reduce clerical costs.
B) Standard costs can be useful in setting prices for finished goods.
C) Standard costs can be used as a means of finding fault with performance.
D) Standard costs can make employees "cost-conscious."

Correct Answer

verifed

verified

The standard direct materials quantity does not include allowances for


A) unavoidable waste.
B) normal spoilage.
C) unexpected spoilage.
D) all of the above are included.

Correct Answer

verifed

verified

If the materials price variance is $3,600 F and the materials quantity and labor variances are each $2,700 U, what is the total materials variance?


A) $3,600 F
B) $2,700 U
C) $900 F
D) $4,050 U

Correct Answer

verifed

verified

The two levels that standards may be set at are


A) normal and fully efficient.
B) normal and ideal.
C) ideal and less efficient.
D) fully efficient and fully effective.

Correct Answer

verifed

verified

The standard quantity allowed for the units produced was 4,500 pounds, the standard price was $2.50 per pound, and the materials quantity variance was $375 favorable.Each unit uses 1 pound of materials.How many units were actually produced?


A) 4,350
B) 4,500
C) 11,625
D) 4,650

Correct Answer

verifed

verified

A favorable variance


A) is an indication that the company is not operating in an optimal manner.
B) implies a positive result if quality control standards are met.
C) implies a positive result if standards are flexible.
D) means that standards are too loosely specified.

Correct Answer

verifed

verified

Standard cost cards are the subsidiary ledger for the Work in Process account in a standard cost system.

Correct Answer

verifed

verified

Showing 21 - 40 of 161

Related Exams

Show Answer