Filters
Question type

Study Flashcards

The Bowden Corporation makes a single product. Only one kind of direct material is used to make this product. The company uses a standard cost system. The company's cost records for June show the following data: The Bowden Corporation makes a single product. Only one kind of direct material is used to make this product. The company uses a standard cost system. The company's cost records for June show the following data:   There were no beginning inventories of direct materials. The actual cost of direct material was: A)  $8.12 per pound B)  $8.00 per pound C)  $7.60 per pound D)  $7.42 per pound There were no beginning inventories of direct materials. The actual cost of direct material was:


A) $8.12 per pound
B) $8.00 per pound
C) $7.60 per pound
D) $7.42 per pound

Correct Answer

verifed

verified

A product's standard cost card specifies that a unit of the product requires 4 direct labor-hours. During September, 3,350 units were made, which was 150 units less than budgeted. The total budgeted direct labor cost for September was $117,600. The direct labor cost incurred during September was $111,850 and 13,450 direct labor-hours were worked. The labor efficiency variance for the month was:


A) $420.00 U
B) $420.00 F
C) $415.80 U
D) $415.80 F

Correct Answer

verifed

verified

Fluegge Inc. has provided the following data concerning one of the products in its standard cost system. Variable manufacturing overhead is applied to products on the basis of direct labor-hours. Fluegge Inc. has provided the following data concerning one of the products in its standard cost system. Variable manufacturing overhead is applied to products on the basis of direct labor-hours.   The company has reported the following actual results for the product for December:   The variable overhead rate variance for the month is closest to: A)  $1,080 U B)  $1,080 F C)  $1,148 U D)  $1,148 F The company has reported the following actual results for the product for December: Fluegge Inc. has provided the following data concerning one of the products in its standard cost system. Variable manufacturing overhead is applied to products on the basis of direct labor-hours.   The company has reported the following actual results for the product for December:   The variable overhead rate variance for the month is closest to: A)  $1,080 U B)  $1,080 F C)  $1,148 U D)  $1,148 F The variable overhead rate variance for the month is closest to:


A) $1,080 U
B) $1,080 F
C) $1,148 U
D) $1,148 F

Correct Answer

verifed

verified

Hardigree Corporation makes a product that has the following direct labor standards: Hardigree Corporation makes a product that has the following direct labor standards:   In May the company's budgeted production was 8,900 units, but the actual production was 8,800 units. The company used 2,820 direct labor-hours to produce this output. The actual direct labor cost was $70,218. The labor efficiency variance for May is: A)  $4,482 U B)  $4,482 F C)  $4,140 U D)  $4,140 F In May the company's budgeted production was 8,900 units, but the actual production was 8,800 units. The company used 2,820 direct labor-hours to produce this output. The actual direct labor cost was $70,218. The labor efficiency variance for May is:


A) $4,482 U
B) $4,482 F
C) $4,140 U
D) $4,140 F

Correct Answer

verifed

verified

Kartman Corporation makes a product with the following standard costs: Kartman Corporation makes a product with the following standard costs:   In June the company's budgeted production was 3,400 units but the actual production was 3,500 units. The company used 22,150 pounds of the direct material and 2,290 direct labor-hours to produce this output. During the month, the company purchased 25,400 pounds of the direct material at a cost of $170,180. The actual direct labor cost was $57,021 and the actual variable overhead cost was $8,931. The company applies variable overhead on the basis of direct labor-hours. The direct materials purchases variance is computed when the materials are purchased. The materials quantity variance for June is: A)  $4,200 F B)  $4,200 U C)  $4,020 U D)  $4,020 F In June the company's budgeted production was 3,400 units but the actual production was 3,500 units. The company used 22,150 pounds of the direct material and 2,290 direct labor-hours to produce this output. During the month, the company purchased 25,400 pounds of the direct material at a cost of $170,180. The actual direct labor cost was $57,021 and the actual variable overhead cost was $8,931. The company applies variable overhead on the basis of direct labor-hours. The direct materials purchases variance is computed when the materials are purchased. The materials quantity variance for June is:


A) $4,200 F
B) $4,200 U
C) $4,020 U
D) $4,020 F

Correct Answer

verifed

verified

The Bowden Corporation makes a single product. Only one kind of direct material is used to make this product. The company uses a standard cost system. The company's cost records for June show the following data: The Bowden Corporation makes a single product. Only one kind of direct material is used to make this product. The company uses a standard cost system. The company's cost records for June show the following data:   There were no beginning inventories of direct materials. The standard cost of direct material for one unit of output is: A)  $2 per unit B)  $16 per unit C)  $8 per unit D)  $10 per unit There were no beginning inventories of direct materials. The standard cost of direct material for one unit of output is:


A) $2 per unit
B) $16 per unit
C) $8 per unit
D) $10 per unit

Correct Answer

verifed

verified

Termeer Inc. has provided the following data concerning one of the products in its standard cost system. Variable manufacturing overhead is applied to products on the basis of direct labor-hours. Termeer Inc. has provided the following data concerning one of the products in its standard cost system. Variable manufacturing overhead is applied to products on the basis of direct labor-hours.   The company has reported the following actual results for the product for August:   The variable overhead rate variance for the month is closest to: A)  $480 F B)  $480 U C)  $476 U D)  $476 F The company has reported the following actual results for the product for August: Termeer Inc. has provided the following data concerning one of the products in its standard cost system. Variable manufacturing overhead is applied to products on the basis of direct labor-hours.   The company has reported the following actual results for the product for August:   The variable overhead rate variance for the month is closest to: A)  $480 F B)  $480 U C)  $476 U D)  $476 F The variable overhead rate variance for the month is closest to:


A) $480 F
B) $480 U
C) $476 U
D) $476 F

Correct Answer

verifed

verified

Showing 241 - 247 of 247

Related Exams

Show Answer