One disadvantage of a U-shaped production line is:


A) It is more compact.
B) It permits better communication among employees.
C) It facilitates teamwork among workers.
D) It increases flexibility of work assignments.
E) It is primarily for small batch sizes.Large batches favour line layout.

Correct Answer

verifed

verified

With group technology items that are similar in either design or manufacturing requirements are grouped into part families.

Correct Answer

verifed

verified

Which type of automation is designed to achieve rapid changeover times when switching from one product to another?


A) Fixed automation
B) Manual automation
C) Robots designed for repetitive,standardized tasks
D) Flexible manufacturing systems

Correct Answer

verifed

verified

The benefits of flexible manufacturing systems (FMS) include all of the following EXCEPT:


A) reduced labour costs.
B) higher flexibility than fixed automation.
C) quick changeover from part to part.
D) less planning and development time required for new systems.
E) more consistent quality.

Correct Answer

verifed

verified

Given the following process layout data for locating four departments (A,B,C,and D)in four areas (1,2,3,and 4): Given the following process layout data for locating four departments (A,B,C,and D)in four areas (1,2,3,and 4):    What is the total flow between departments B and D? What is the total flow between departments B and D?

Correct Answer

verifed

verified

In process layouts production resources are arranged according to similarity of function.

Correct Answer

verifed

verified

Which one of the following is not one of the steps used in manufacturing layout design?


A) Location of receiving and shipping
B) Presence of customers
C) Special requirements of equipment
D) Allowing space for machines and material handling (e.g.forklifts)
E) Determine expected workflow between departments.

Correct Answer

verifed

verified

Layouts involving combinations of product (line)layouts and cellular layouts are not possible.

Correct Answer

verifed

verified

Given the following process layout data for locating four departments (A,B,C,and D)in four areas (1,2,3,and 4): Given the following process layout data for locating four departments (A,B,C,and D)in four areas (1,2,3,and 4):    If department C must be located in area 1,what layout will minimize the total distance loads will be moved each month? If department C must be located in area 1,what layout will minimize the total distance loads will be moved each month?

Correct Answer

verifed

verified

C in 1; A ...

View Answer

A company needs to rebalance a product layout for producing a redesigned product.They plan to use the assembly line 6 hours in order to meet projected demand of 2,160 license plates each day.The following table describes the tasks involved in the production of this product: A company needs to rebalance a product layout for producing a redesigned product.They plan to use the assembly line 6 hours in order to meet projected demand of 2,160 license plates each day.The following table describes the tasks involved in the production of this product:   For output to equal projected demand,what will be the idle time at the second workstation of the assembly line that uses the minimum number of workstations? A) 0 seconds B) 1 second C) 2 seconds D) 3 seconds E) 5 seconds For output to equal projected demand,what will be the idle time at the second workstation of the assembly line that uses the minimum number of workstations?


A) 0 seconds
B) 1 second
C) 2 seconds
D) 3 seconds
E) 5 seconds

Correct Answer

verifed

verified

A swim lane diagram is a process map in which each function/role's activities are in its row/lane.

Correct Answer

verifed

verified

Which of the following is true about process layouts when they are compared to product layouts?


A) Lower in-process inventories
B) Lower unit handling costs
C) Lower variety of processing requirements
D) Less vulnerable to shut down because of mechanical failure
E) Lower skill levels among labour force

Correct Answer

verifed

verified

A production line is to be designed for a job with three tasks.The task times are 0.6 minutes,1.8 minutes,and 1.2 minutes.If the necessary cycle time is 1.2 minutes per unit,what is the theoretical minimum number of workstations?


A) 2.0
B) 3.0
C) 3.6
D) 4.0
E) 4.2

Correct Answer

verifed

verified

QRS Corp.is designing a product layout for a new product.They plan to use this production line ten hours a day in order to meet forecasted demand of 900 units per day.The following table describes the tasks necessary to produce this product: QRS Corp.is designing a product layout for a new product.They plan to use this production line ten hours a day in order to meet forecasted demand of 900 units per day.The following table describes the tasks necessary to produce this product:   For output to equal forecasted demand,what will be the efficiency of the production line that uses the least number of workstations? A) 81% B) 90% C) 95% D) 85% E) 100% For output to equal forecasted demand,what will be the efficiency of the production line that uses the least number of workstations?


A) 81%
B) 90%
C) 95%
D) 85%
E) 100%

Correct Answer

verifed

verified

The maker of the world-famous Widget needs to design a product layout for a new product,the amazing "Thatsit".The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 units per day.The following table describes the tasks involved in the production of a "Thatsit". The maker of the world-famous Widget needs to design a product layout for a new product,the amazing  Thatsit .The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 units per day.The following table describes the tasks involved in the production of a  Thatsit .   For output to equal projected demand,what will the percentage idleness be of the production line that uses the minimum number of workstations? A) 10% B) 5% C) 3% D) 1% E) 0% For output to equal projected demand,what will the percentage idleness be of the production line that uses the minimum number of workstations?


A) 10%
B) 5%
C) 3%
D) 1%
E) 0%

Correct Answer

verifed

verified

Which type of automation is least suited for a wide variety of products?


A) Fixed automation
B) Programmable automation
C) Flexible automation
D) Flexible manufacturing systems

Correct Answer

verifed

verified

A company needs to locate three departments (X,Y,and Z) in the three areas (I,II,and III) of a new facility.They want to minimize interdepartmental transportation costs,which are expected to be $.50 per load per metre moved.An analyst has prepared the following distances and flow matrices: A company needs to locate three departments (X,Y,and Z) in the three areas (I,II,and III) of a new facility.They want to minimize interdepartmental transportation costs,which are expected to be $.50 per load per metre moved.An analyst has prepared the following distances and flow matrices:   If departments X,Y,and Z were to be located in areas I,II,and III,respectively,what would be the total distance (in metres) loads would be moved each week? A) 4,000 B) 4,500 C) 7,000 D) 8,000 E) 9,000 If departments X,Y,and Z were to be located in areas I,II,and III,respectively,what would be the total distance (in metres) loads would be moved each week?


A) 4,000
B) 4,500
C) 7,000
D) 8,000
E) 9,000

Correct Answer

verifed

verified

What is the process flow diagram for services called?


A) Process diagram
B) Flow chart
C) Service interaction diagram
D) Service blueprint
E) Product/process layout

Correct Answer

verifed

verified

Programmable automation requires less changeover time than flexible automation.

Correct Answer

verifed

verified

A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day.The tasks necessary to produce this product: A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day.The tasks necessary to produce this product:   If the company desires that output rate equal demand,what is the minimum number of workstations needed? A) 3 B) 4 C) 5 D) 6 E) 7 If the company desires that output rate equal demand,what is the minimum number of workstations needed?


A) 3
B) 4
C) 5
D) 6